The Alberta Utilities Commission (AUC) is seeking feedback as part of its review of Rule 024: Rules Respecting Micro-Generation. A bulletin was issued on July 20, 2026, outlining the full details. The engagement aims to gather input on information requirements for extraordinary cost disputes and identify opportunities to improve the microgeneration application and connection process, particularly for larger microgeneration projects.

The AUC is inviting feedback on:

  • Information requirements for extraordinary cost disputes.
  • Timelines for application approval and project connection.
  • Changes to project costs and technical requirements during the connection process.
  • Communication between customers and distribution facility owners.
  • Other microgeneration-related issues.

Interested participants can download the response documents found on the side of this page and submit feedback to engage@auc.ab.ca using the subject line “Rule 024 engagement.” Responses are due by Monday, August 17, 2026.

Please note that there are two separate response documents (Rule 024 comment matrix and Rule 024 questionnaire). Participants may submit either or both, depending on their areas of interest and experience. Participants may also answer as many or as few questions as may be relevant.

This is a public engagement, and submissions may be posted on the AUC website with contact information aside from names removed. Feedback received will help inform potential improvements to the microgeneration connection process.

For more information, contact engage@auc.ab.ca.

  • July 20, 2026

    The AUC opened its written engagement on July 20, 2026.

  • August 17, 2026

    The engagement period closes, and the AUC will begin its review of feedback provided throughout the engagement process.